Brighton Boulevard Construction Project

Brighton Blvd. ProjectProject Overview

ESCO Construction Company is installing a new irrigation waterline on Brighton Blvd. beginning in March 2018. ESCO will try not to impact day-to-day activities in the neighborhood during the construction of the new water system. The nature of this work requires them to temporarily divert or detour vehicle and pedestrian traffic in the vicinity of the water main installation. All necessary permits have been secured from the city/county/state, etc. and all reasonable accommodations will be made to provide vehicle and pedestrian access to homes. There will be construction equipment and construction workers in the work zones during normal construction work hours (7 a.m.-5 p.m.). Please allow 3-4 weeks for the work to be completed. (Click on photo to enlarge.)

Traffic Control Update

Starting April 6, Brighton Rd. will be closed to thru traffic between 104th Ave. and 96th Ave. from 8 a.m. to 4 p.m. This will be in effect weekdays from April 6 through May 11. ESCO has reached out to the local businesses/residents to ensure they know what is going on in this section during this time period.

Closure Update

Brighton Road will be closed from Tuesday, April 24,  8 a.m., through Wednesday, April 25, 4 p.m., with a detour in place. ESCO Construction Company will be working across both lanes of Brighton Road.

Contact

Please feel free to ask any questions of our onsite supervisor or Project Information Manager (PIM). The contact info for the PIM is:

Kyle Griffin
303.674.3385 (office) | 720.788.7003 (cell)
Kgriffin@escomailbox.com

If problems or concerns arise that the contractor does not resolve, please contact the Adams County Construction Manager at 720.523.6961.