2019 Street Paving Project

Project Overview

This Adams County project focuses on improving various paved streets identified as priorities for rehabilitation. The project encompasses three different areas in the County:

Adams County awarded this project to Martin Marietta Materials for $5,361,774. Weather permitting, the project completion is anticipated in late October 2019.

Project Update

The project is now complete!

On Thursday, Nov. 14, crews finished the striping operation in the Todd Creek area. This work was the last scheduled activity as part of the Adams County 2019 Street Paving project.

This project focused on improving various paved streets identified as priorities for rehabilitation, in three different areas:

  • Area 1 - Hayesmount Rd.
  • Area 2 – Eagle Shadow Subdivision
  • Area 3 – Todd Creek

We want to thank the public for their patience during construction.

Todd Creek Paving
Todd Creek: Active Construction
New Pavement - Todd Creek
Todd Creek: New Pavement
Todd Creek: Newly Paved Street
Todd Creek: Newly Paved Street
Hayesmount Road
Hayesmount Road

Contact Information

If you have additional questions or comments, please contact us at the phone number or email address below:

Phone: 720.572.4475, ext. 8
Email: adamscountypaving2019@zoho.com

If problems or concerns arise that the contractor is not resolving, please contact the Adams County Construction Manager at 720.523.6965.